IT Change Management Policy
Overview
Applications and systems are increasingly more complex in their function, interaction, and form. There is an increasing dependency between resources and applications that can negatively impact operations if not managed and orchestrated in an organized fashion. Effective management and communication of updates, maintenance, and regular releases help to minimize customer impacts. From time-to-time systems require outages for planned upgrades, maintenance, or fine-tuning. Managing these changes is a critical part of providing a stable infrastructure.
Purpose
The purpose of this policy is to manage IT changes in a well-communicated, planned, and predictable manner that minimizes unplanned outages and unforeseen system issues. Effective IT change management requires planning, communication, monitoring, rollback, and follow-up procedures to reduce negative impact to the user community.
Scope
This policy applies to all Howard Community College personnel involved in application or systems changes, updates, or patches.
Policy
A. General
- All system and application changes in Information Technology, Academic Departments, and any college entity utilizing information assets (e.g. operating system, computing hardware, networks, applications, data centers) are subject to this policy and shall follow unit change management procedures.
- The following general requirements shall be met in the change management process:
- Scheduled change calendars and departmental communications operational procedures shall be developed to inform stakeholders of upcoming application and system changes that impact system availability or operations.
- Regular planned changes shall be communicated to all stakeholders at least monthly through a communication mechanism specified by the Chief Information Officer (CIO).
- Unplanned outages shall be communicated immediately to stakeholders with regular updates on progress towards resolution and resumption of service.
- Regular system and application patching schedules shall be communicated to users and performed in such a way as to minimize system downtime and user productivity.
- Changes affecting computing environmental facilities (e.g., air-conditioning, water, heat, plumbing, electricity, and alarms) shall be reported to or coordinated with the Facilities Department. Stakeholders shall be notified through normal college change management communications.
- Processes shall ensure that production data is not unnecessarily replicated or used in non-production environments.
- Device configurations shall be backed up and rollback procedures must exist prior to implementing a change.
B. IT Change Management Committee
- An IT Change Management Committee shall convene to discuss system changes, interactions, and any perceived issues. This committee shall consist of network and systems staff, application development owners, and chaired by the CIO or their designee. The following procedures shall be implemented by the committee:
- The committee shall meet on a schedule determined by the CIO but shall minimally meet monthly to discuss plans for future updates and patching.
C. Change Request Management
- The following procedure shall be implemented surrounding the change management process:
- Change requests shall be submitted for all changes, both scheduled and unscheduled
- All scheduled change requests shall be submitted in accordance with departmental change management procedures so that the Change Management Committee has time to review the request, determine and review potential failures, and make the decision to allow or delay the system update
- Change requests shall receive Change Management Committee approval before proceeding with the change
- A change review must be completed for each change, whether scheduled or unscheduled, and whether successful or unsuccessful
D. Change Management Denials
- The CIO or their designee may deny a scheduled or unscheduled change for reasons including, but not limited to:
- Inadequate change planning or unit testing
- Lack of stakeholder acceptance (where applicable)
- System integration or interoperability concerns
- Missing or deficient roll-back plans
- Security implications and risk
- Timing of the change negatively impacting key business processes
- Timeframes do not align with resource scheduling (e.g. late-night, weekends, holidays, or during special events)
E. Administration
- A Change Management Log Form shall be maintained for all changes. This log must contain, but is not limited to:
- Date of submission and date of change
- Owner and custodian contact information
- Nature of the change
- Indications of success or failure
- Notes and follow-ons
Audit Controls and Management
- On-demand documented procedures and evidence of practice shall be in place for this operational policy as part of the college IT governance requirements. Satisfactory examples of evidence and compliance include:
- Historical logs of change events
- Archival Change Management Committee meeting minutes
- Anecdotal documentation and communications showing regular compliance with the policy
Enforcement
Any college personnel found in policy violation may be subject to disciplinary action, up to and including termination.
Distribution
This policy is to be distributed to all Howard Community College personnel and contractors using college owned information resources.
This standard shall be subject to periodic review to ensure relevancy.
Date: June 25, 2026
Approved By: Senior Leadership Team